CNOOC starts production from Luda 10-1 adjustment project

July 21, 2015

HONG KONG -- CNOOC has announced that the Luda 10-1 comprehensive adjustment project has commenced production.

The Luda 10-1 oilfield is located in Liaodong Bay of Bohai with an average water depth of approximately 30 m.

In addition, to fully utilize the existing facilities of Luda 10-1, this adjustment project has also built one wellhead platform. There are currently 13 producing wells producing approximately 3,300 bpd of crude oil. The adjustment project is expected to reach its ODP designed peak production of approximately 6,000 bpd of crude oil in 2016.

Luda 10-1 is an independent oilfield in which CNOOC holds 100% interest and acts as the operator.